Cancer Institute Loses Workers to Delays, Restarts Hiring

The Charlotte Kimelman Cancer Institute must recruit new staff after employees left during repeated postponements of the facility's reopening.

Modern medical imaging equipment including a linear accelerator in a hospital treatment room with the US Virgin Islands flag visible, clinical lighting, no people
Illustration (AI-generated)

ST. THOMAS: Workers recruited for the Charlotte Kimelman Cancer Institute have departed for other positions as construction delays pushed back the facility's planned reopening, prompting hospital leadership to launch a fresh recruitment drive for essential roles.

Dr. Jerry Smith, board chairman of the V.I. Government Hospitals and Health Facilities Corporation, reported the staffing challenge to lawmakers during a Tuesday Committee on Health, Hospitals, and Human Services hearing. The original timeline had guided the hiring process, but the extended delays prompted resignations.

"Those individuals elected to move on. We are now re-recruiting for some critical positions to be back at the facility," Dr. Smith said. Senator Avery Lewis responded that the development was disappointing.

The cancer center shuttered following the 2017 hurricanes and was slated to resume operations in the second quarter of 2026. Failed procurement rounds for minor medical equipment, furniture, fixtures and information technology items derailed that schedule.

Darryl Smalls, executive director of facilities and capital development for the Territorial Hospital Redevelopment Team, reported progress on procurement. The team has now "successfully procured 100% of the 542 items that were included in the minor medical solicitations," he told the committee.

Total spending on equipment has reached $6,992,259.84, with deliveries of more than 1,000 items anticipated. The linear accelerator and CT simulator are already at the site, though additional components must arrive before testing and certification can proceed.

Smalls told lawmakers that by after January 2027, "95 to 100 percent of the equipment that is required for the facility" should be in place. Those missing components have been ordered and paid for, he added.

How does this story make you feel?

Sources The Virgin Islands Consortium