St. Croix power cuts follow propane terminal repairs as generation crisis deepens

Emergency work at Richmond Power Plant knocked out six feeders Tuesday, forcing WAPA to implement rolling three-hour blackouts across the island.

A large industrial power generation facility with cooling towers and propane storage tanks under a tropical sky, the US Virgin Islands flag flying prominently, photographed at dusk with industrial lighting casting long shadows across the complex
Illustration (AI-generated)

ST. CROIX. The Water and Power Authority imposed rotating three-hour blackouts across St. Croix on Tuesday after contractor Saintnals performed emergency repairs on the Richmond Power Plant's propane terminal, taking the facility offline and disrupting power to thousands of customers.

The outages began early Tuesday morning. At 8:25 a.m., six feeders had lost power: 4A, 6B and 6A. By 10 a.m., the list had grown to include Feeders 9A, 9B and 10B. WAPA initially expected the work to finish around 3 p.m., but by 5:30 p.m. the authority had not confirmed the terminal was operational again and switched to announcing three-hour rotations based on system conditions.

By evening, Feeders 4A, 6A, 6B and 10B had been restored and were set to stay powered until 7 p.m. Feeders 9A and 9B were scheduled to receive electricity at 7 p.m. for three hours. However, Feeders 1A, 2A, 3A and 8B remained offline with no restoration times given. WAPA said it was prioritising critical feeders with help from St. Croix's three solar farms.

The St. Croix crisis coincided with a separate generation problem in the St. Thomas-St. John district, where WAPA took an additional unit offline Monday night for urgent repairs. Throughout Tuesday, surging customer demand forced the authority to extend outages and reschedule rotations multiple times, pushing some feeders' restoration back by up to two hours.

These disruptions add to an existing generation shortage at the Randolph E. Harley Power Plant on St. Thomas. WAPA CEO Karl Knight told lawmakers Monday that Wรคrtsilรค Engines 4 and 6 had been repaired. He expressed hope that Engine 5 could return within a week, while Engine 7 might be back in December.

To address the capacity gap, WAPA and the Office of Disaster Recovery are considering a six-month lease of the KPS-51 Metin Bey power ship, which would supply at least 30 megawatts at Krum Bay. The arrangement would cost 2.85 million dollars upfront plus 11 cents per kilowatt-hour, with funding still being discussed. Knight said the extra capacity would free existing generators for maintenance and repairs.

Customers are also grappling with estimated billing. Knight acknowledged Monday that estimates based on past usage likely do not match current consumption. He said accounts would receive credits but gave no timeline or details on how the adjustments would be worked out.

WAPA plans to replace 55,000 meters starting in January, beginning on St. John and then moving to St. Thomas and St. Croix.

How does this story make you feel?

Sources The Virgin Islands Consortium