Charlotte Amalie Harbor Dredging Starts Friday Under $41.9M Contract

The V.I. Port Authority says work begins November 27, with equipment already positioned and surveys complete.

A large dredging barge and support vessels moored in a Caribbean harbor at dawn, with the US Virgin Islands flag visible on a nearby structure, equipment and machinery on deck ready for operations
Illustration (AI-generated)

Work to deepen Charlotte Amalie Harbor will commence Friday, November 27, according to an announcement from the V.I. Port Authority on Tuesday. Equipment has arrived in the territory and preliminary surveys have been finished for the project, which is critical to the cruise industry.

Orion Marine Construction holds the contract, valued at up to $41.9 million. The Port Authority board endorsed the award in March, and the agreement took effect on June 5 with a 365-day timeline beginning when dredging starts.

Executive Director Ava Penn said the work will tackle the harbor entrance channel, the turning basin and the West Indian Company Limited berthing pocket at Havensight. The goal is to make the waterway deeper, improve how large vessels can maneuver and meet the demands of cruise operators.

This represents a shift from the Port Authority's September projection, which had targeted October 12 for the start. No explanation was given for the delay.

How operations will unfold

Work will happen every day of the week. The main channel and turning basin will see activity from sunrise to sunset, while the WICO berthing pocket and bulkhead will be worked on at night.

Phase one runs from November 2026 through March 2027. During this period, material deemed unsuitable for beaches will be removed from the entrance channel, turning basin and WICO berthing pocket. Vessels will carry this material to the Gordon A. Finch Molasses Pier in Krause Lagoon on St. Croix's south shore for temporary storage and dewatering. Trucks will then transport it to a quarry north of Henry E. Rohlsen Airport.

Preparation is already underway. Supporting barges reached St. Croix on November 14 and 15, and crews are clearing the temporary stockpile site. Silt fences went in last weekend, and stabilized site entrances were built this week.

On St. Thomas, the dredge, barges and survey vessel arrived at Crown Bay on November 17. A survey on November 19 and 20 recorded the current state of the harbor.

Phase two and funding sources

From March through October 2027, phase two will extract beach-quality material from the entrance channel. Vessels will move this to Crown Bay Cargo Port, where it will be unloaded and trucked to the former Addelita Cancryn Junior High School property for storage.

Most of the old school site has been cleared. Contractor Custom Builders demolished structures there starting in June at a cost of $2.5 million.

The Port Authority said it will work with Orion, WICO, cruise lines and other maritime operators to reduce disruptions and allow scheduled ship movements. Work timing and sequence may shift due to cruise schedules, weather, marine operations or other factors.

The Port Authority identified $17 million in legislative funds under Act 8787 and $6 million under Act 9068 for the dredging. When approving the contract in March, the authority said it would seek $18.9 million through marine bonds once they are issued and collected.

How does this story make you feel?

Sources The Virgin Islands Consortium ยท St. John Source