The V.I. Waste Management Authority is counting on a $40 million injection from Governor Albert Bryan Jr.'s bonding plan to stabilize its finances and prevent waste contractors from halting collections across the territory.
At a board meeting on Tuesday, Executive Director Hannibal Ware revealed that the Authority has issued citations for violations but never collected the resulting fines. "Nobody's ever gone for the money. There was no process to get the money," Ware said. His office is now building a collection system to recover those funds.
Contractors are already signalling distress. Sleepy's Trucking halted collection services on St. Thomas over unpaid invoices, and Collections Manager Petula Stevens reported that other haulers have warned of potential work stoppages if payment delays continue.
Ware, who arrived at the Authority in September 2025 from his role as Inspector General of the U.S. Small Business Administration, is pushing the Public Services Commission to adopt weight-based tipping fees instead of volume-based charges. He described the Authority as facing a $15 million shortfall at the start of each fiscal year and said it remains "inadequately funded."
The agency is simultaneously restructuring how it operates. Attorney Devin Carrington, formerly Commissioner of the Department of Licensing and Consumer Affairs, reviewed the Authority's internal workings and uncovered more than 40 existing policies and procedures across divisions, though some departments had none whatsoever. "The way we do business is helter skelter, the way we feel today, and that's no way to run an agency as important as this," Carrington said.
This overhaul reflects lessons from the U.S. Department of Housing and Urban Development's freeze on federal funding to the V.I. Housing Finance Authority over policy shortcomings. That freeze is now cascading into Waste Management, delaying planned Convenience Centers in Bournefield, Red Hook, and Cancryn on St. Thomas, as well as upgrades to the Susannaberg Transfer Station on St. John.
Ware is managing multiple infrastructure emergencies. The LBJ Force Main, which lifts sewage from Christiansted, has fragile pipes that rupture frequently and demand costly emergency repairs. An oil remediation requirement at the Concordia Convenience Center carries a price tag exceeding $500,000, straining a project budgeted at just over $1 million.
On a positive front, an air curtain incinerator arrived on St. Thomas last month to tackle the green waste problem. The Bovoni landfill stopped accepting green waste following a 2023 fire that cost the government roughly $1 million in firefighting. Manufacturer training is set for December 3 and 4. The Authority is also deepening a recycling partnership with Replastic on St. Croix, which converts plastic into consumer goods at no cost to the Authority.