A leading U.S. senator has pressed for immediate federal action to address severe power shortages across the U.S. Virgin Islands, faulting the governor's reluctance to seek emergency status that could unlock additional resources.
Mike Lee, a Utah Republican who chairs the Senate Committee on Energy and Natural Resources, made the call on November 26 via social media. He said the Army Corps of Engineers should be "mission-assigned immediately via an emergency declaration to deploy temporary generation." Lee pointed to "decades of mismanagement and deferred maintenance" at the Water and Power Authority and called the situation "dire."
"Residents need reliable power now," Lee wrote.
Governor Albert Bryan Jr. has resisted declaring an emergency, contending that doing so would not meaningfully speed repairs. At a November 9 briefing, he noted that WAPA already held federal funding, technical support and generators on-site but required time to finish work. He did acknowledge that an emergency declaration could facilitate an Environmental Protection Agency waiver for connecting additional equipment.
On November 19, the governor announced a $5.04 million award from the Interior Department for WAPA, covering a Water Island cable replacement, protection relays and spare parts. He stated that "fixing WAPA takes more than declaring an emergency."
Bryan's recent schedule included a November 16-17 visit to the Invest Ghana Summit in Accra, which Government House characterized as an investment-recruitment effort aimed at attracting teachers and nurses.
The utility's operational challenges have intensified. At a November 25 emergency board session, WAPA reported roughly 36 megawatts of available capacity against a projected peak demand of 54 megawatts. All four second-phase Wärtsilä engines were offline, and three first-phase engines were running below normal capacity while awaiting overdue major maintenance.
St. Croix experienced separate difficulties on November 24 when a defective propane-terminal control panel and low diesel reserves triggered extended blackouts. WAPA said it repaired the terminal and restored power across the island by around 11:30 p.m.
Governor-elect Stacey Plaskett has also pushed for intervention. In an October 25 letter to WAPA's board, she requested an emergency order from the U.S. Department of Energy under Section 202(c) of the Federal Power Act. She has committed to declaring a WAPA emergency when she takes office on January 4 and urged Bryan to act beforehand.
Future infrastructure projects face additional complications. A Virgin Islands Housing Finance Authority grid report from October identified four WAPA resiliency initiatives in limbo, with a HUD suspension blocking completion of three agreements and postponing soil testing for a proposed St. Thomas battery installation.
Lee's statement does not by itself authorize an Army Corps deployment. Under FEMA's emergency-power protocol, unmet power requests flow through relevant emergency-management structures, with FEMA assigning the Corps through a formal mission assignment. A territorial emergency declaration alone would not automatically send federal generators.
Comments
No comments yet. Be the first.